Kensington mixed-use

Client type
Tessler Group
Duration
16 Months
Service type
Construction management
Kensington mixed-use
Client goal

Open the shops in phases while the offices were still going up

Tessler needed rent coming in from the ground-floor shops as early as possible, without the street losing its parking or its foot traffic.

‍

At a glance
  • Client goal: Open shops in phases
  • Delivery deadline: Anchor tenant open by November
  • Site constraint: Morning-only deliveries on Kensington
The challenge

Reworking live construction without delaying openings

Two tenants changed their layouts after the electrical and ventilation were already in. That meant reworking finished areas while three other trades were working overhead.

‍

We resequenced the upper floors around the retail work, so the shops could open on time without trades stacking up or anyone working under an open deck.

How we built it

Phased handovers

Each shop was fenced off, finished and handed over on its own date. Shoppers walked past a quiet hoarding wall while the structure kept rising above them.

‍

Key milestones
  • Foundations complete / Week 7 / Drainage redesign approved before the frame went up
  • First shops open / Week 26 / Two tenants trading under a finished canopy
  • Final handover / March 2025 / Offices occupied, street fully reopened
Final result

Shops open, street intact

All six shops opened on or before their dates, the anchor tenant three weeks early for the holiday season, with the sidewalk open the whole time.

‍

By the numbers
  • 18,400 / Square Feet Delivered / Six shops plus two office floors
  • 3 Weeks Early / Anchor Tenant Opening / In time for holiday shopping
  • 16 Months / Active Construction / Phased handovers throughout
Quote Up
Our restaurant was the first to open on the block, on the exact date they gave us six months earlier.
Ethan Wallace
Ethan Wallace
Restaurant owner